Dept. of Trans. PROGRESS Serial No. Contract No. 23-355-14-37 01-436404 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 39% Location: Federal Project: 01-DN-101-35.8/36.5 ACNH-Q101(398) Progress payment No. 016 Payment period ending: 12-20-23 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,630,199.80 1,910,334.02 2. a. Extra Work 28,674.19 6,428.34 b. Adustment Comp. 3. Materials on Hand 300,547.30 -172,120.94 4. Earned Subject to Retention 16,959,421.29 1,744,641.42 5. Mobilization 6,851,400.00 0.00 6. Total Work Completed 23,510,273.99 7. Deductions -13,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 23,797,821.29 1,741,641.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,741,641.42