Dept. of Trans. PROGRESS Serial No. Contract No. 24-081-09-17 01-436404 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 49% Location: Federal Project: 01-DN-101-35.8/36.5 ACNH-Q101(398) Progress payment No. 019 Payment period ending: 03-20-24 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,883,610.66 852,534.36 2. a. Extra Work 354,260.79 291,817.01 b. Adustment Comp. -215,531.95 -215,531.95 3. Materials on Hand 438,292.00 -2.00 4. Earned Subject to Retention 20,460,631.50 928,817.42 5. Mobilization 6,851,400.00 0.00 6. Total Work Completed 26,873,739.50 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,302,031.50 928,817.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 928,817.42