Dept. of Trans. PROGRESS Serial No. Contract No. 25-024-13-56 01-436404 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 75% Location: Federal Project: 01-DN-101-35.8/36.5 ACNH-Q101(398) Progress payment No. 029 Payment period ending: 01-20-25 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,613,819.29 243,240.00 2. a. Extra Work 1,441,668.42 -105,653.43 b. Adustment Comp. -205,072.35 0.00 3. Materials on Hand 497,001.98 5,826.00 4. Earned Subject to Retention 33,347,417.34 143,412.57 5. Mobilization 6,851,400.00 0.00 6. Total Work Completed 39,701,815.36 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 40,196,817.34 143,412.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 143,412.57