Dept. of Trans. PROGRESS Serial No. Contract No. 25-293-14-47 01-436404 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 89% Location: Federal Project: 01-DN-101-35.8/36.5 ACNH-Q101(398) Progress payment No. 038 Payment period ending: 10-20-25 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,418,509.31 4,532,695.81 2. a. Extra Work 2,493,010.63 25,704.26 b. Adustment Comp. -207,919.40 0.00 3. Materials on Hand 126,263.00 -83,193.00 4. Earned Subject to Retention 55,829,863.54 4,475,207.07 5. Mobilization 7,212,000.00 0.00 6. Total Work Completed 62,915,600.54 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 63,031,863.54 4,465,207.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,465,207.07