Dept. of Trans. PROGRESS Serial No. Contract No. 26-083-09-33 01-436404 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 90% Location: Federal Project: 01-DN-101-35.8/36.5 ACNH-Q101(398) Progress payment No. 043 Payment period ending: 03-20-26 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 56,979,960.42 134,340.00 2. a. Extra Work 3,094,451.44 169,583.53 b. Adustment Comp. -207,919.40 0.00 3. Materials on Hand 36,718.00 36,718.00 4. Earned Subject to Retention 59,903,210.46 340,641.53 5. Mobilization 7,212,000.00 0.00 6. Total Work Completed 67,078,492.46 7. Deductions -1,000.00 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 67,114,210.46 343,641.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 343,641.53