Dept. of Trans. PROGRESS Serial No. Contract No. 05-206-07-29 01-442004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 58% 01-DN-101-39.6/46.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-05 TIDEWATER CONTRACTORS INC P O BOX 1956 BROOKINGS OR 97415 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 255,683.12 239,478.87 2.a. Extra Work 91,885.45 91,885.45 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 347,568.57 331,364.32 5. Mobilization 6. Total Work Completed 347,568.57 7. Deductions -2,000.00 -2,000.00 8. a.Contract Retentions -18,038.29 -16,417.86 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 327,530.28 312,946.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 312,946.46