Dept. of Trans. PROGRESS Serial No. Contract No. 07-306-12-34 01-443104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 69% 01-MEN-175-1.1/1.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-19-07 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 02324 Total Estimate This Estimate 1. Contract Itms Without Mobil. 682,714.59 199,922.32 2.a. Extra Work 34,215.74 34,215.74 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 716,930.33 234,138.06 5. Mobilization 6. Total Work Completed 716,930.33 7. Deductions -2,500.00 -2,500.00 8. a.Contract Retentions -35,846.52 -11,706.91 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 678,583.81 219,931.15 10. Reduction Amt to Escrow 11. Payment to Escrow 35,840.00 12. Net Pymt. this Estimate 219,931.15