Dept. of Trans. PROGRESS Serial No. Contract No. 09-267-09-20 01-447504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 71% 01-MEN-101-81.4/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-17-09 PARSONS BROS ROCKERIES CLIFORNIA INC 1588 BEDELL COURT ROSEVILLE CA 95747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 127,614.38 70,189.28 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 127,614.38 70,189.28 5. Mobilization 23,750.00 0.00 6. Total Work Completed 151,364.38 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 151,364.38 70,189.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,189.28