Dept. of Trans. PROGRESS Serial No. Contract No. 14-203-12-56 01-450904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 15% 01-HUM-169-13.6/23.4 Federal Project: HSST-S169(6) Progress payment No. 04 Payment period ending: 07-17-14 STEELHEAD CONSTRUCTORS INC P O BOX 997 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 198,553.00 83,182.00 2.a. Extra Work 117,722.45 23,440.84 b. Adjustment Comp. 3. Materials on Hand 86,428.69 86,428.69 4. Earned Subject to Retention 402,704.14 193,051.53 5. Mobilization 262,500.00 87,500.00 6. Total Work Completed 578,775.45 7. Deductions -2,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 663,204.14 278,551.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 278,551.53