Dept. of Trans. PROGRESS Serial No. Contract No. 12-201-10-10 01-4518A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 100% 01-HUM-101-12.9/13.1 Federal Project: 01-HUM-101-0.0 NONE Progress payment No. 05 Payment period ending: 07-19-12 NORWOOD CONSTRUCTION 5301 BYRON HOT SPRINGS RD NE BYRON CA 94514 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 107,807.00 6,570.00 2.a. Extra Work 89,233.69 43,301.38 b. Adjustment Comp. 33,033.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 230,074.54 49,871.38 5. Mobilization 6. Total Work Completed 230,074.54 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 230,074.54 49,871.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,871.38