Dept. of Trans. PROGRESS Serial No. Contract No. 09-113-09-26 01-452404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 5% 9% 01-HUM-96-16.0/18.7 Federal Project: OTS Progress payment No. 03 Payment period ending: 04-20-09 STEWART ENGINEERING INC P O BOX 990010 REDDING CA 96099 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,623.96 40,623.96 2.a. Extra Work 1,309.27 1,309.27 b. Adjustment Comp. 3. Materials on Hand 74,347.38 38,357.38 4. Earned Subject to Retention 117,280.61 80,290.61 5. Mobilization 60,000.00 60,000.00 6. Total Work Completed 102,933.23 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 177,280.61 140,290.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 140,290.61