Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-334-18-17 01-457204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-HUM-101-83.4/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-10-06 WAHLUND CONSTRUCTION INC 830 HILMA DRIVE EUREKA CA 95503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 321,748.50 10,472.50 2.a. Extra Work 11,031.02 11,031.02 b. Adjustment Comp. 25,000.00 25,000.00 3. Materials on Hand 4. Earned Subject to Retention 357,779.52 46,503.52 5. Mobilization 6. Total Work Completed 357,779.52 7. Deductions -1,047.25 640.25 8. a.Contract Retentions -15,563.80 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 15,563.80 15,563.80 9. Total pay to Contractor 356,732.27 62,707.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 62,707.57