Dept. of Trans. PROGRESS Serial No. Contract No. 14-112-12-07 01-459704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 31% 01-HUM-101-98.1/100.7 Federal Project: NH-Q101(231) Progress payment No. 06 Payment period ending: 04-17-14 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT SUITE D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 705,115.50 239,305.00 2.a. Extra Work 11,913.53 1,873.72 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 717,029.03 241,178.72 5. Mobilization 185,250.00 0.00 6. Total Work Completed 902,279.03 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 902,279.03 241,178.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 241,178.72