Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-016-12-48 01-463924 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 01-HUM-999 HSST-PG X023-035-E Progress payment No. 020 Payment period ending: 12-19-17 APEX FENCE CO INC 19896 ALEXANDER AVENUE ANDERSON CA 96007 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,542,442.57 31,180.00 2. a. Extra Work 416,573.64 59,490.36 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,959,016.21 90,670.36 5. Mobilization 125,000.00 0.00 6. Total Work Completed 4,084,016.21 7. Deductions -20,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,064,016.21 70,670.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 70,670.36