Dept. of Trans. PROGRESS Serial No. Contract No. 11-024-12-14 01-464004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 20% 38% 01-HUM-101-T0.2/R126.0 Federal Project: HSN-Q101(162) H-Q101(162) Progress payment No. 05 Payment period ending: 01-20-11 WAHLUND CONSTRUCTION INC 830 HILMA DRIVE EUREKA CA 95503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 772,358.25 641,818.25 2.a. Extra Work 257.65 257.65 b. Adjustment Comp. 3. Materials on Hand 521,502.60 521,502.60 4. Earned Subject to Retention 1,294,118.50 1,163,578.50 5. Mobilization 92,250.70 92,250.70 6. Total Work Completed 864,866.60 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,386,369.20 1,255,829.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,255,829.20