Dept. of Trans. PROGRESS Serial No. Contract No. 12-237-13-19 01-464204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 21% 01-MEN-999 Federal Project: ACHS-X045(22) STPG-X045(22) Progress payment No. 03 Payment period ending: 08-20-12 CORAL CONSTRUCTION COMPANY P O BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 337,824.75 318,924.75 2.a. Extra Work 17,948.31 17,948.31 b. Adjustment Comp. 3. Materials on Hand 290,947.88 145,473.94 4. Earned Subject to Retention 646,720.94 482,347.00 5. Mobilization 341,816.63 341,816.63 6. Total Work Completed 697,589.69 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 978,537.57 814,163.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 814,163.63