Dept. of Trans. PROGRESS Serial No. Contract No. 12-326-13-37 01-464204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 41% 01-MEN-999 Federal Project: ACHS-X045(22) STPG-X045(22) Progress payment No. 06 Payment period ending: 11-20-12 CORAL CONSTRUCTION COMPANY P O BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,915,142.95 453,282.75 2.a. Extra Work 140,102.49 94,110.66 b. Adjustment Comp. -4,532.40 0.00 3. Materials on Hand 649,480.00 162,630.00 4. Earned Subject to Retention 2,700,193.04 710,023.41 5. Mobilization 432,967.73 0.00 6. Total Work Completed 2,483,680.77 7. Deductions -3,000.00 12,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,130,160.77 722,023.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 722,023.41