Dept. of Trans. PROGRESS Serial No. Contract No. 12-356-11-22 01-464204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 46% 45% 01-MEN-999 Federal Project: ACHS-X045(22) STPG-X045(22) Progress payment No. 07 Payment period ending: 12-19-12 CORAL CONSTRUCTION COMPANY P O BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,266,430.15 351,287.20 2.a. Extra Work 247,452.83 107,350.34 b. Adjustment Comp. -4,532.40 0.00 3. Materials on Hand 620,734.57 -28,745.43 4. Earned Subject to Retention 3,130,085.15 429,892.11 5. Mobilization 455,755.50 22,787.78 6. Total Work Completed 2,965,106.08 7. Deductions -5,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,580,840.65 450,679.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 450,679.89