Dept. of Trans. PROGRESS Serial No. Contract No. 12-355-07-50 01-465304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 35% 01-DN-101-R2.7/8.8 Federal Project: ACHN-EQ10(121) Progress payment No. 03 Payment period ending: 12-19-12 S T RHOADES CONSTRUCTION INC P O BOX 494520 REDDING CA 96002 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 229,151.00 103,920.00 2.a. Extra Work 330.69 330.69 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 229,481.69 104,250.69 5. Mobilization 6. Total Work Completed 229,481.69 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 229,481.69 104,250.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 104,250.69