Dept. of Trans. SEMI-FINAL Serial No. Contract No. 21-012-08-57 01-466304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 01-MEN-101-R0.1/R9.6 ACNH-Q101(359) Progress payment No. 012 Payment period ending: 11-11-20 ARGONAUT CONSTRUCTORS PO BOX 639 SANTA ROSA CA 95402 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,704,184.76 0.00 2. a. Extra Work 941,980.05 23,736.20 b. Adustment Comp. -269,758.92 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,376,405.89 23,736.20 5. Mobilization 732,500.00 0.00 6. Total Work Completed 10,108,905.89 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,108,905.89 23,736.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,736.20