Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-224-09-28 01-467504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-LAK-175-8.3/19.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-23-09 NORTHWEST PAVING 8115 SECLUDED VALLEY DRIVE REDDING CA 96001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 460,779.53 144,387.79 2.a. Extra Work 10,775.51 10,775.51 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 471,555.04 155,163.30 5. Mobilization 6. Total Work Completed 471,555.04 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 470,555.04 154,163.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 154,163.30