Dept. of Trans. PROGRESS Serial No. Contract No. 10-298-08-38 01-470214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 96% 01-HUM-101-R40.9/R42.2 Federal Project: ER-43F4(4) Progress payment No. 22 Payment period ending: 10-20-10 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,690,063.92 74,357.00 2.a. Extra Work 194,426.00 10,718.65 b. Adjustment Comp. -67,153.76 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,817,336.16 85,075.65 5. Mobilization 550,000.00 0.00 6. Total Work Completed 5,367,336.16 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,362,336.16 85,075.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 85,075.65