Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-068-12-11 01-470604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-LAK-29-18.5/19.1 Federal Project: NONE Progress payment No. 06 Payment period ending: 11-16-09 ARGONAUT CONSTRUCTORS 1236 CENTRAL AVENUE SANTA ROSA CA 95401 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 574,470.11 -45,875.00 2.a. Extra Work 249,054.87 161,642.47 b. Adjustment Comp. 9,742.47 4,342.47 3. Materials on Hand 4. Earned Subject to Retention 833,267.45 120,109.94 5. Mobilization 6. Total Work Completed 833,267.45 7. Deductions -3,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 830,267.45 120,109.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 120,109.94