Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-024-15-58 01-472004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-LAK-29-27.6/28.1 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-30-07 STEINY AND COMPANY INC P O BOX 3008 VALLEJO CA 94590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 419,690.90 12,640.24 2.a. Extra Work 1,274.07 1,274.07 b. Adjustment Comp. 5,309.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 426,273.97 13,914.31 5. Mobilization 5,000.00 0.00 6. Total Work Completed 431,273.97 7. Deductions -17,000.00 0.00 8. a.Contract Retentions -20,352.53 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 20,352.53 0.00 9. Total pay to Contractor 414,273.97 13,914.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,914.31