Dept. of Trans. PROGRESS Serial No. Contract No. 10-298-13-09 01-472104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 89% 01-HUM-299-R21.5/ .0 Federal Project: ER-4316(4) Progress payment No. 06 Payment period ending: 10-20-10 CALEX ENGINEERING COMPANY 23651 PINE STREET NEWHALL CA 91321 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 803,480.96 122,808.75 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -18,056.00 4. Earned Subject to Retention 803,480.96 104,752.75 5. Mobilization 125,000.00 0.00 6. Total Work Completed 928,480.96 7. Deductions -15,816.30 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 912,664.66 104,752.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 104,752.75