Dept. of Trans. PROGRESS Serial No. Contract No. 11-202-14-28 01-472604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 29% 01-MEN-1-82.1/82.3 Federal Project: ER-43K0(4) Progress payment No. 03 Payment period ending: 07-20-11 VALENTINE CORPORATION P O BOX 9337 SAN RAFAEL CA 94912 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 610,089.24 425,131.24 2.a. Extra Work 16,192.25 2,055.49 b. Adjustment Comp. 3. Materials on Hand 0.00 -77,315.10 4. Earned Subject to Retention 626,281.49 349,871.63 5. Mobilization 78,433.90 16,512.40 6. Total Work Completed 704,715.39 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 704,715.39 366,384.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 366,384.03