Dept. of Trans. PROGRESS Serial No. Contract No. 10-173-13-22 01-472804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 13% 01-MEN-1-95.2/102.4 Federal Project: ER-43JO(4) Progress payment No. 01 Payment period ending: 06-18-10 GREEN RIGHT O WAY CONSTRUCTORS INC P O BOX 1119 WILLITS CA 95490 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,656.00 32,656.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 32,656.00 32,656.00 5. Mobilization 22,500.00 22,500.00 6. Total Work Completed 55,156.00 7. Deductions -4,916.25 -4,916.25 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 50,239.75 50,239.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,239.75