Dept. of Trans. PROGRESS Serial No. Contract No. 09-267-10-11 01-474304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 68% 01-HUM-96-21.8/ .0 Federal Project: ER-43H(4) Progress payment No. 04 Payment period ending: 09-17-09 R BROWN CONSTRUCTION COMPANY INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 269,247.00 40,347.00 2.a. Extra Work 40,967.12 8,390.27 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 310,214.12 48,737.27 5. Mobilization 50,000.00 2,500.00 6. Total Work Completed 360,214.12 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 360,214.12 51,237.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 51,237.27