Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 15-092-08-02 01-474904 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 7% Location: Federal Project: 01-MEN-1-70.5 ER-43M6(4) Progress payment No. 002 Payment period ending: 03-20-15 GRANITE CONSTRUCTION COMPANY 1324 S. STATE STREET UKIAH CA 95482 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 423,438.80 0.00 2. a. Extra Work 19,356.33 19,356.33 b. Adustment Comp. 3. Materials on Hand 391,647.47 0.00 4. Earned Subject to Retention 834,442.60 19,356.33 5. Mobilization 375,000.00 0.00 6. Total Work Completed 817,795.13 7. Deductions -1,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,208,442.60 19,356.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,356.33