Dept. of Trans. PROGRESS Serial No. Contract No. 15-203-14-03 01-474904 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 38% Location: Federal Project: 01-MEN-1-70.5 ER-43M6(4) Progress payment No. 006 Payment period ending: 07-20-15 GRANITE CONSTRUCTION COMPANY 1324 S. STATE STREET UKIAH CA 95482 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,149,809.65 371,730.85 2. a. Extra Work 71,204.81 -20,023.34 b. Adustment Comp. 72,913.00 38,813.00 3. Materials on Hand 297,545.47 -94,102.00 4. Earned Subject to Retention 1,591,472.93 296,418.51 5. Mobilization 475,000.00 0.00 6. Total Work Completed 1,768,927.46 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,066,472.93 296,418.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 296,418.51