Dept. of Trans. PROGRESS Serial No. Contract No. 12-326-12-51 01-475504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 99% 01-HUM-36-23.3/28.2 Federal Project: STP4-3L00(4E) Progress payment No. 05 Payment period ending: 11-20-12 PACIFIC EARTHSCAPE 2415 SUTTER ROAD MC KINLEYVILLE CA 95519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 877,325.71 81,594.07 2.a. Extra Work 115,209.18 75,766.91 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 992,534.89 157,360.98 5. Mobilization 37,000.00 0.00 6. Total Work Completed 1,029,534.89 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,029,534.89 157,360.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 157,360.98