Dept. of Trans. PROGRESS Serial No. Contract No. 09-293-09-22 01-475704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 32% 01-HUM-36-40.4/ .0 Federal Project: ER-4312(4) Progress payment No. 03 Payment period ending: 10-20-09 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 361,519.25 148,907.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -25,000.00 4. Earned Subject to Retention 361,519.25 123,907.50 5. Mobilization 114,000.00 0.00 6. Total Work Completed 475,519.25 7. Deductions -14,365.42 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 461,153.83 123,907.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 123,907.50