Dept. of Trans. PROGRESS Serial No. Contract No. 09-299-10-43 01-476304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 100% 01-MEN-162-11.6/11.8 Federal Project: ER-43H7(4) Progress payment No. 03 Payment period ending: 10-20-09 ARGONAUT CONSTRUCTORS P O BOX 639 SANTA ROSA CA 95402 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 533,021.07 86,398.40 2.a. Extra Work 15,459.67 15,459.67 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 548,480.74 101,858.07 5. Mobilization 67,000.00 0.00 6. Total Work Completed 615,480.74 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 615,480.74 101,858.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 101,858.07