Dept. of Trans. FINAL Serial No. Contract No. 10-174-17-45 01-476304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-162-11.6/11.8 Federal Project: ER-43H7(4) Progress payment No. 07 Payment period ending: 12-07-09 ARGONAUT CONSTRUCTORS P O BOX 639 SANTA ROSA CA 95402 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 575,216.57 0.00 2.a. Extra Work 189,590.71 0.00 b. Adjustment Comp. -20,854.54 0.00 3. Materials on Hand 4. Earned Subject to Retention 743,952.74 0.00 5. Mobilization 67,000.00 0.00 6. Total Work Completed 810,952.74 7. Deductions 0.00 1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 810,952.74 1,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,000.00