Dept. of Trans. PROGRESS Serial No. Contract No. 14-234-07-37 01-476604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 44% 01-MEN-128-34.5/35.5 Federal Project: ER-43M5(4) Progress payment No. 04 Payment period ending: 08-20-14 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT STE D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 781,389.75 414,072.60 2.a. Extra Work 117,671.32 21,592.52 b. Adjustment Comp. -6,674.77 -6,674.77 3. Materials on Hand 4. Earned Subject to Retention 892,386.30 428,990.35 5. Mobilization 247,000.00 52,000.00 6. Total Work Completed 1,139,386.30 7. Deductions -2,000.00 6,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,137,386.30 486,990.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 486,990.35