Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-344-10-43 01-477404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-HUM-96-22.9/ .0 Federal Project: 01-HUM-96-28.3/ .0 NONE Progress payment No. 09 Payment period ending: 10-27-09 MURPHY INDUSTRIAL COATINGS INC 2704 GUNDRY AVENUE SIGNAL HILL CA 90755 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,479,994.00 9,780.00 2.a. Extra Work 40,408.20 30,672.85 b. Adjustment Comp. 53,400.97 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,573,803.17 40,452.85 5. Mobilization 100,000.00 0.00 6. Total Work Completed 1,673,803.17 7. Deductions -15,000.00 -10,000.00 8. a.Contract Retentions -76,667.52 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 76,667.52 76,667.52 9. Total pay to Contractor 1,658,803.17 107,120.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 107,120.37