Dept. of Trans. PROGRESS Serial No. Contract No. 10-083-10-52 01-478104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 83% 01-MEN-101-1.5/6.5 Federal Project: ER-43H6(4) Progress payment No. 07 Payment period ending: 03-22-10 NORTH BAY CONSTRUCTION INC 431 PAYRAN STREET PETALUMA CA 94952 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,230,988.86 -12,950.00 2.a. Extra Work 140,247.60 4,533.80 b. Adjustment Comp. 1,239.15 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,372,475.61 -8,416.20 5. Mobilization 11,900.00 0.00 6. Total Work Completed 1,384,375.61 7. Deductions 0.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,384,375.61 11,583.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,583.80