Dept. of Trans. PROGRESS Serial No. Contract No. 11-235-13-06 01-478304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 49% 01-HUM-169-18.0/19.8 Federal Project: ER-43J9(4) Progress payment No. 04 Payment period ending: 08-19-11 ENGINEERED SOIL REPAIRS INC 1267 SPRINGBROOK ROAD WALNUT CREEK CA 94597 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 642,982.33 353,819.72 2.a. Extra Work 26,204.73 -4,705.71 b. Adjustment Comp. 3. Materials on Hand 0.00 -6,151.00 4. Earned Subject to Retention 669,187.06 342,963.01 5. Mobilization 58,491.50 0.00 6. Total Work Completed 727,678.56 7. Deductions -4,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 723,678.56 342,963.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 342,963.01