Dept. of Trans. PROGRESS Serial No. Contract No. 12-263-10-23 01-479204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 37% 01-LAK-29-20.1/20.4 Federal Project: 01-LAK-53-0.0/3.1 STPX-330(77E) Progress payment No. 04 Payment period ending: 09-17-12 TEICHERT CONSTRUCTION P O BOX 1890 DAVIS CA 956171890 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,299,854.78 1,101,266.48 2.a. Extra Work 35,096.76 12,984.53 b. Adjustment Comp. -760.00 -760.00 3. Materials on Hand 4. Earned Subject to Retention 1,334,191.54 1,113,491.01 5. Mobilization 292,125.00 138,375.00 6. Total Work Completed 1,626,316.54 7. Deductions -38,000.00 -18,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,588,316.54 1,233,866.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,233,866.01