Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-317-10-51 01-479804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-HUM-101-75.1/78.7 Federal Project: NONE Progress payment No. 04 Payment period ending: 09-23-08 STIMPEL WIEBELHAUS ASSOCIATES INC P O BOX 492335 REDDING CA 960492335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 883,830.00 79,014.37 2.a. Extra Work 11,128.96 11,128.96 b. Adjustment Comp. 37,053.63 0.00 3. Materials on Hand 4. Earned Subject to Retention 932,012.59 90,143.33 5. Mobilization 24,000.00 0.00 6. Total Work Completed 956,012.59 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions -27,141.98 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 27,141.98 0.00 9. Total pay to Contractor 946,012.59 100,143.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,143.33