Dept. of Trans. PROGRESS Serial No. Contract No. 11-327-07-17 01-480204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 82% 01-MEN-1-59.3/ .0 Federal Project: ATPP-001(553) Progress payment No. 05 Payment period ending: 11-18-11 FEDCO CONSTRUCTION INC 3510 BROOKS AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,322,324.47 571,972.58 2.a. Extra Work 36,912.77 30,755.57 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,359,237.24 602,728.15 5. Mobilization 62,000.00 0.00 6. Total Work Completed 1,421,237.24 7. Deductions -3,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,418,237.24 602,728.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 602,728.15