Dept. of Trans. PROGRESS Serial No. Contract No. 07-268-13-38 01-480714 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 27% 01-HUM-101-32.0/33.2 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-20-07 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,281,094.45 955,051.95 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -160,867.00 4. Earned Subject to Retention 1,281,094.45 794,184.95 5. Mobilization 351,500.00 74,000.00 6. Total Work Completed 1,632,594.45 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -70,118.93 -21,427.98 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,552,475.52 836,756.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 836,756.97