Dept. of Trans. PROGRESS Serial No. Contract No. 10-294-07-35 01-482704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 75% 01-DN-199-R18.2/R18.6 Federal Project: ACHS-P199(32) NH-P199(32) Progress payment No. 02 Payment period ending: 10-20-10 HI TECH ROCKFALL CONSTRUCTION INC P O BOX 674 FOREST GROVE OR 971160674 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 788,623.20 271,765.00 2.a. Extra Work b. Adjustment Comp. 2,153.20 2,153.20 3. Materials on Hand 4. Earned Subject to Retention 790,776.40 273,918.20 5. Mobilization 57,000.00 2,850.00 6. Total Work Completed 847,776.40 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 847,776.40 276,768.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 276,768.20