Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-160-12-41 01-482804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-VAR Federal Project: NONE Progress payment No. 08 Payment period ending: 02-21-11 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 149,904.53 0.00 2.a. Extra Work 306,612.91 0.00 b. Adjustment Comp. 4,700.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 461,217.44 0.00 5. Mobilization 30,000.00 0.00 6. Total Work Completed 491,217.44 7. Deductions -1,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 490,217.44 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00