Dept. of Trans. PROGRESS Serial No. Contract No. 09-146-11-12 01-483104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 56% 01-LAK-29-9.7/ .0 Federal Project: 01-LAK-29-20.4/ .0 NONE Progress payment No. 01 Payment period ending: 05-20-09 DEBRUIN CONSTRUCTION INC P O BOX 1355 FRENCH CAMP 95231 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 69,543.45 69,543.45 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 69,543.45 69,543.45 5. Mobilization 10,000.00 10,000.00 6. Total Work Completed 79,543.45 7. Deductions -1,784.26 -1,784.26 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 77,759.19 77,759.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,759.19