Dept. of Trans. PROGRESS Serial No. Contract No. 08-268-15-33 01-484804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 0% 01-MEN-1-15.3/20.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-19-08 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 02399 Total Estimate This Estimate 1. Contract Itms Without Mobil. 816,123.07 812,706.82 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 816,123.07 812,706.82 5. Mobilization 6. Total Work Completed 816,123.07 7. Deductions 8. a.Contract Retentions -40,806.15 -40,464.52 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 775,316.92 772,242.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 772,242.30