Dept. of Trans. PROGRESS Serial No. Contract No. 11-202-09-46 01-485904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 60% 69% 01-MEN-1-104.9/105.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 07-20-11 N Y BLASTCO INC 14710 S MAPLE AVENUE GARDENA CA 90248 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 335,240.86 242,192.39 2.a. Extra Work 5,867.69 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 341,108.55 242,192.39 5. Mobilization 24,440.00 6,110.00 6. Total Work Completed 365,548.55 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 365,548.55 248,302.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 248,302.39