Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-027-13-36 01-486804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-101-30.9/R31.9 Federal Project: NONE Progress payment No. 06 Payment period ending: 08-12-09 PROFESSIONAL CONSTRUCTION SERVICES 4070 NELSON AVENUE, SUITE A CONCORD, CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,314,778.70 3,428.50 2.a. Extra Work 1,869.46 1,869.46 b. Adjustment Comp. -20,613.43 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,296,034.73 5,297.96 5. Mobilization 6,700.50 0.00 6. Total Work Completed 1,302,735.23 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -46,445.45 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 46,445.45 0.00 9. Total pay to Contractor 1,302,735.23 15,297.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,297.96