Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-057-10-21 01-486904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 01-MEN-1-60.8/62.3 Federal Project: NONE Progress payment No. 07 Payment period ending: 12-11-08 ARGONAUT CONSTRUCTORS P O BOX 639 SANTA ROSA CA 95402 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,616,300.87 6,577.60 2.a. Extra Work 55,265.99 8,352.41 b. Adjustment Comp. -11,900.88 -11,900.88 3. Materials on Hand 4. Earned Subject to Retention 1,659,665.98 3,029.13 5. Mobilization 190,000.00 0.00 6. Total Work Completed 1,849,665.98 7. Deductions -1,000.00 23,237.00 8. a.Contract Retentions -80,902.49 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 80,902.49 0.00 9. Total pay to Contractor 1,848,665.98 26,266.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,266.13