Dept. of Trans. PROGRESS Serial No. Contract No. 22-262-12-55 01-488014 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 69% Location: Federal Project: 01-DN-199-6.5/36.3 NONE Progress payment No. 008 Payment period ending: 09-20-22 GR SUNDBERG, INC. 5211 BOYD RD ARCATA CA 95521 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 864,061.30 280,120.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -98,491.14 4. Earned Subject to Retention 864,061.30 181,628.86 5. Mobilization 66,000.00 0.00 6. Total Work Completed 930,061.30 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 930,061.30 183,628.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 183,628.86